Inspection reveals minor water damage in Taunton High School gym floor

An inspection of the new Taunton High School field house floor has revealed minor water damage in a handful of floor boards.

“They’re not on the playing surface,” Superintendent Julie Hackett said.What are some types of moulds? “They’re outside of the playing surface,Find the cheapest chickencoop online through and buy the best hen houses and chook pens in Australia. and there’s nothing really visible that we can see … It’s four to five boards right now, but one is too many.”

The damage to the floor boards is apparently the result of a leaky roof at the newly renovated high school, which along with the adjacent Parker Middle School recently underwent $112 million worth of construction and renovations over a four-year span.Dimensional Mailing magiccubes for Promotional Advertising,

The new floor is less than three months old.

After learning of the leak, the city had the roof repaired and had an inspector examine the field house floor for damage.

“There are 4-5 boards affected that are cupped,” Michael DiNatale of All American Sports Group said in a March 13 email to the School Department. “These boards may or may not need to be replaced depending on how much moisture they absorbed. We recommend monitoring the boards over the next 4-6 weeks and see if the boards flatten out.If you have a kidneystone, If not, they will need to be replaced.”

Hackett said she wouldn’t classify the damage as severe.

“We have to protect the investment that we made,” she said. “I think we’ll know better in four-to-six weeks. We’ll continue to monitor it, and if anything needs to be changed, we’ll hold the appropriate parties responsible for the replacement costs.”

Last month, workers discovered small holes in the rubber membrane covering the high school’s flat roof. City officials speculated that the ruptures could have been caused by anything from a worker accidentally stepping on a nail to seagulls smashing shellfish against the rooftop.

On older roofs, the outer layer was typically made up of crushed stone, rather than a sheet of rubber.

After the leaks were discovered, Stanley Roofing, the company that installed the roof, performed repairs.Pfister werkzeugbau AG aus Mönchaltorf ist Ihr Partner bei der Herstellung von Werkzeugen und Spritzformen.

“We’ve had no further leaks since the day we had the issue,” Hackett said. “They did do patching, and it seems to have taken care of the issue. They continue to monitor the rooftops and do periodic checks to make sure it’s secure. So far, so good.”

Mayor Thomas Hoye Jr. said he will work with Hackett and the city Building Department to “work through proper channels and pursue remediation from the responsible parties,” if the leaks reappear. He suggested the possibility of having an independent contractor inspect the roof.

“Far too much money has been spent through the (School Building Authority) and also by our taxpayers to allow this to happen,” he said. “What we will not do is sit back and do nothing.”